Continuing the Track to New Heights
The station is really beginning to take shape. The structural steel assembly has been completed and we are pouring the concrete deck this week. The stairs, walls and roof work will continue over the next few weeks.
The electrical and pneumatic work is moving along quite well and the relocation of underground utilities in the station area is finished. Soon Leviathan will be power ready.
The track and column assembly is well underway. The curve after the main drop and the long airtime hill are now complete and we are heading south towards the front gate plaza. The landscape of the park is really starting to transform with each new piece of track. To date we have installed 50% of the track sections.